A resource is a necessary asset which functions to (help) complete a specific task(s) or project.

When deducing a resource, consider a 'full-time employee' whose actual work corresponds to ~170 working days per year (or 3.27 days per week).

ConsiderationDifferenceTotal (days)
Working week (5 days, 52 weeks)+260260
Bank holidays-8252
Holiday (typical in UK)-25227
Non-working time (training, sickness)-15212
Margins (meetings, loo breaks, etc.)×0.8~170
Proof of a full-time employee's days worked